Chris Anderson

Do youI have an estimated time that zone SPNE01-113 will be available for service?

User Avatar

10:32AM April 08, 2020

HolstonConnect Admin
At this time, the interstate crossing required to provide service to your area has been delayed due to COVID-19. While having already approved crossing the interstate with the fiber, the actual date to complete the task was halted by the State of Tennessee to a date yet to be determined. The crossing requires TDOT, Contractor, Tennessee Highway Patrol, and HolstonConnect employees to all work parallel to each other in close proximity.